New Engineering Contract
NEC was first published in 1993 as the New Engineering Contract. It is a suite of construction contracts intended to promote partnering and collaboration between the contractor and client. It was developed as a reaction to other more traditional forms of construction contract which have been portrayed by some as adversarial.
The intentions of NEC contracts include:
- Stimulating good management.
- Being clear and simple, written in plain English, in the present tense and without legal terminology.
- Being useable in wide variety of situations from minor works to major projects
The suite of documents now include:
- NEC4: Alliance Contract
- NEC4: Design Build and Operate Contract
- NEC4: Dispute Resolution Service Contract
- NEC4: Engineering and Construction Contract
- NEC4: Engineering and Construction Short Contract
- NEC4: Engineering and Construction Short Subcontract
- NEC4: Facilities Management Contract
- NEC4: Facilities Management Short Contract
- NEC4: Facilities Management Short Subcontract
- NEC4: Facilities Management Subcontract
- NEC4: Framework Contract
- NEC4: Professional Service Contract
- NEC4: Professional Service Short Contract
- NEC4: Professional Service Subcontract
- NEC4: Supply Contract
- NEC4: Supply Short Contract
- NEC4: Term Service Contract
- NEC4: Term Service Short Contract
- NEC4: Term Service Subcontract
The Engineering and Construction Contract has 6 options:
- NEC4: Engineering and Construction Contract Option A priced contract with activity schedule
- NEC4: Engineering and Construction Contract Option B: priced contract with bill of quantities
- NEC4: Engineering and Construction Contract Option C: target contract with activity schedule
- NEC4: Engineering and Construction Contract Option D: target contract with bill of quantities
- NEC4: Engineering and Construction Contract Option E: cost reimbursable contract
- NEC4: Engineering and Construction Contract Option F: management contract
There are a number of articles relating to NEC on Designing Buildings:
- Accepted programme.
- Activity schedule
- Compensation event.
- Cost reimbursable contract.
- Defined cost.
- Delay damages.
- Disallowed cost.
- Early contractor involvement.
- Early warning notice.
- Key dates.
- Latham Report.
- NEC contract change management systems.
- NEC contracts - road development and management schemes.
- NEC contracts and collaborative working.
- NEC early contractor involvement.
- NEC early warning notices - a tool of mutual benefit.
- NEC3.
- NEC4.
- NEC Option A: Priced contract with activity schedule.
- NEC Option B: Priced contract with bill of quantities.
- NEC Option C: Target contract with activity schedule.
- NEC Option D: Target contract with bill of quantities.
- NEC Option E: Cost reimbursable contract.
- Period for reply.
- Term Contract.
- The NEC and the Z clause.
- Time Risk Allowance.
- Z clauses.
[edit] Related articles on Designing Buildings
Featured articles and news
Shortage of high-quality data threatening the AI boom
And other fundamental issues highlighted by the Open Data Institute.
Data centres top the list of growth opportunities
In robust, yet heterogenous world BACS market.
Increased funding for BSR announced
Within plans for next generation of new towns.
New Towns Taskforce interim policy statement
With initial reactions to the 6 month policy update.
Heritage, industry and slavery
Interpretation must tell the story accurately.
PM announces Building safety and fire move to MHCLG
Following recommendations of the Grenfell Inquiry report.
Conserving the ruins of a great Elizabethan country house.
BSRIA European air conditioning market update 2024
Highs, lows and discrepancy rates in the annual demand.
50 years celebrating the ECA Apprenticeship Awards
As SMEs say the 10 years of the Apprenticeship Levy has failed them.
Nominations sought for CIOB awards
Celebrating construction excellence in Ireland and Northern Ireland.
EPC consultation in context: NCM, SAP, SBEM and HEM
One week to respond to the consultation on reforms to the Energy Performance of Buildings framework.
CIAT Celebrates 60 years of Architectural Technology
Find out more #CIAT60 social media takeover.
The BPF urges Chancellor for additional BSR resources
To remove barriers and bottlenecks which delay projects.
Flexibility over requirements to boost apprentice numbers
English, maths and minimumun duration requirements reduced for a 10,000 gain.
A long term view on European heating markets
BSRIA HVAC 2032 Study.
Humidity resilience strategies for home design
Frequency of extreme humidity events is increasing.
National Apprenticeship Week 2025
Skills for life : 10-16 February
Comments
[edit] To make a comment about this article, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.