New Engineering Contract
NEC was first published in 1993 as the New Engineering Contract. It is a suite of construction contracts intended to promote partnering and collaboration between the contractor and client. It was developed as a reaction to other more traditional forms of construction contract which have been portrayed by some as adversarial.
The intentions of NEC contracts include:
- Stimulating good management.
- Being clear and simple, written in plain English, in the present tense and without legal terminology.
- Being useable in wide variety of situations from minor works to major projects
The suite of documents now include:
- NEC4: Alliance Contract
- NEC4: Design Build and Operate Contract
- NEC4: Dispute Resolution Service Contract
- NEC4: Engineering and Construction Contract
- NEC4: Engineering and Construction Short Contract
- NEC4: Engineering and Construction Short Subcontract
- NEC4: Facilities Management Contract
- NEC4: Facilities Management Short Contract
- NEC4: Facilities Management Short Subcontract
- NEC4: Facilities Management Subcontract
- NEC4: Framework Contract
- NEC4: Professional Service Contract
- NEC4: Professional Service Short Contract
- NEC4: Professional Service Subcontract
- NEC4: Supply Contract
- NEC4: Supply Short Contract
- NEC4: Term Service Contract
- NEC4: Term Service Short Contract
- NEC4: Term Service Subcontract
The Engineering and Construction Contract has 6 options:
- NEC4: Engineering and Construction Contract Option A priced contract with activity schedule
- NEC4: Engineering and Construction Contract Option B: priced contract with bill of quantities
- NEC4: Engineering and Construction Contract Option C: target contract with activity schedule
- NEC4: Engineering and Construction Contract Option D: target contract with bill of quantities
- NEC4: Engineering and Construction Contract Option E: cost reimbursable contract
- NEC4: Engineering and Construction Contract Option F: management contract
There are a number of articles relating to NEC on Designing Buildings:
- Accepted programme.
- Activity schedule
- Compensation event.
- Cost reimbursable contract.
- Defined cost.
- Delay damages.
- Disallowed cost.
- Early contractor involvement.
- Early warning notice.
- Key dates.
- Latham Report.
- NEC contract change management systems.
- NEC contracts - road development and management schemes.
- NEC contracts and collaborative working.
- NEC early contractor involvement.
- NEC early warning notices - a tool of mutual benefit.
- NEC3.
- NEC4.
- NEC Option A: Priced contract with activity schedule.
- NEC Option B: Priced contract with bill of quantities.
- NEC Option C: Target contract with activity schedule.
- NEC Option D: Target contract with bill of quantities.
- NEC Option E: Cost reimbursable contract.
- Period for reply.
- Term Contract.
- The NEC and the Z clause.
- Time Risk Allowance.
- Z clauses.
[edit] Related articles on Designing Buildings
Featured articles and news
Confirming previously announced funding, and welfare changes amid adjusted growth forecast.
Scottish Government responds to Grenfell report
As fund for unsafe cladding assessments is launched.
CLC and BSR process map for HRB approvals
One of the initial outputs of their weekly BSR meetings.
Architects Academy at an insulation manufacturing facility
Programme of technical engagement for aspiring designers.
Building Safety Levy technical consultation response
Details of the planned levy now due in 2026.
Great British Energy install solar on school and NHS sites
200 schools and 200 NHS sites to get solar systems, as first project of the newly formed government initiative.
600 million for 60,000 more skilled construction workers
Announced by Treasury ahead of the Spring Statement.
The restoration of the novelist’s birthplace in Eastwood.
Life Critical Fire Safety External Wall System LCFS EWS
Breaking down what is meant by this now often used term.
PAC report on the Remediation of Dangerous Cladding
Recommendations on workforce, transparency, support, insurance, funding, fraud and mismanagement.
New towns, expanded settlements and housing delivery
Modular inquiry asks if new towns and expanded settlements are an effective means of delivering housing.
Building Engineering Business Survey Q1 2025
Survey shows growth remains flat as skill shortages and volatile pricing persist.
Construction contract awards remain buoyant
Infrastructure up but residential struggles.
Warm Homes Plan and existing energy bill support policies
Breaking down what existing policies are and what they do.
A dynamic brand built for impact stitched into BSRIA’s building fabric.
Comments
[edit] To make a comment about this article, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.